Check your bill first: Lodi Electric or PG&E
Start with the name at the top of your electric bill, not the city in your mailing address.
Inside Lodi city limits, power comes from Lodi Electric Utility (LEU), owned by the City. LEU sets its own solar rules for how big the system can be, what an export earns, whether one array can serve two meters, and who approves the design first.
Outside city limits, the wires usually belong to PG&E. Ava Community Energy, the community power supplier, now serves unincorporated San Joaquin County, and Ava states that Lodi is not eligible because the city has its own municipal utility. A vineyard near Woodbridge or a parcel near Acampo can carry a Lodi mailing address and still sit on PG&E wires with Ava supply. The bill settles it; a ZIP code can't.
California's statewide net billing rules cover PG&E, SCE and SDG&E customers, not LEU's. Lodi's solar rates page says net metering closed to new systems in September 2017, and the City no longer pays solar rebates.
EcoGen's California solar incentives guide says the same for every city utility in the state: its own board sets the credit for extra power, the state's Solar Billing Plan does not apply, and a PG&E example won't estimate your credits. Get the rule in writing before you choose a size. Lodi's is posted, and the table below sums it up.
If a proposal for a Lodi city address mentions "net billing", "NEM 3.0" or hourly export credits, ask which utility it assumed. Lodi isn't the only nearby case of a non-PG&E utility writing its own cap; the irrigation district that serves River Islands does too.
Lodi Electric's solar rules in one table
Every row comes from LEU's own documents, mainly its Photovoltaic Solar Installation Guidelines, effective July 2026.
| LEU rule | What it says | What it changes in your quote |
|---|---|---|
| Size cap | Estimated yearly production may meet, but not exceed, the meter's previous 12 months of use, checked with the CSI EPBB calculator. New homes: livable square feet × 0.002 kW | Sized to your history, not your roof |
| Export credit | Schedule EP: exports earn LEU's avoided cost, $0.0843/kWh from July 1, 2026 to June 30, 2027, reset every July 1 | Surplus earns little; on-site use matters more |
| Settlement | Leftover credits carry forward to the next monthly bill | Summer credit lowers later bills |
| Ownership | No power-purchase agreements (PPAs). Leases are allowed as financing | No pay-per-kWh offers |
| Several meters | No aggregate or virtual net metering | One array per meter |
| Approval order | The contractor submits the design to LEU's PowerClerk portal for pre-approval, up to two weeks, before the City issues a permit | No permit until LEU signs off |
| Meter fee | $839 for single-phase (60–200 A) service, posted for July 2026–June 2027 | Once per system |
| Equipment | New, CEC-listed equipment; a performance meter; renewable energy credits (RECs) belong to LEU | Used or unlisted panels are out |
| Rebates | None from the City or LEU | Question any "Lodi rebate" |
Schedule EP is LEU's billing schedule for solar customers since September 2017. Solar you use as it's produced never shows on the bill; grid power is billed at retail; exports earn LEU's avoided cost, what LEU would otherwise pay for that power. That's why the credit is low and moves every July.
The CSI EPBB calculator is the California Solar Initiative's Expected Performance-Based Buydown tool. If its estimate exceeds your 12-month use, the guidelines say the application will not proceed. Ask your installer to show the EPBB result beside your usage history.
Ignore any "20% rule for solar in Lodi". LEU's rule is 100% of your meter's last 12 months.
Planning an EV or an electric water heater? LEU's cap looks back, not forward: the estimate is checked against the past 12 months of use, so a Lodi quote can't size in next year's car. LEU's FAQ says you can re-apply later to add panels. Ask the installer how a later addition would work: a new LEU application once the added load shows in your history, and whether the inverter has room for more panels. (Outside the city, PG&E's rules allow up to 50% above annual load with an attestation; inside LEU there is no such allowance.)
Used at home, a kWh is worth up to four times an export
Should you size to LEU's cap and count on selling surplus? No. Value the power you use.
LEU's posted residential rates (summary effective July 1, 2024, still the linked current document) bill delivered power in three monthly tiers:
| Tier | Winter month | Summer month | Rate per kWh |
|---|---|---|---|
| Tier 1 | 0–391 kWh | 0–481 kWh | 14.28¢ |
| Tier 2 | 392–782 kWh | 482–962 kWh | 15.81¢ |
| Tier 3 | Above 782 kWh | Above 962 kWh | 33.66¢ |
Add a $19.50 monthly customer charge and the energy cost adjustment (ECA), a per-kWh charge LEU sets each month. In July, August and September 2026 it was 4.96¢, 5.13¢ and 3.17¢. Don't let a quote freeze one month's value.
Solar used at home removes your top-tier kWh first. If your household crosses into Tier 3, each of those kWh is worth 33.66¢ before the ECA, about four times (3.99×) the 8.43¢ export credit; the ECA widens the gap. If you stay in Tier 1, the ratio is about 1.7× (14.28¢ against 8.43¢). Either way, a kWh used at home beats one exported.
Treat 8.43¢ as this year's number. LEU resets it each July 1; since July 2020 it has ranged from 7.72¢ to 13.52¢. A 25-year table that holds it flat is guessing, so ask for the export line shown separately.
A system sized exactly to yearly use still exports at midday and imports after sunset. Under Schedule EP those exports come back as 8.43¢ credits, not as kWh you can draw later at retail.
One array, several meters: the city line decides
Can one array cover the house plus a shop, barn or well pump on its own meter? The answer flips at the city line.
Inside city limits: no. In Resolution 2016-125, the City Council found that aggregation would shift costs and ruled that Lodi will not allow net energy metering aggregation in LEU's territory. The July 2026 guidelines keep that line. An array offsets only the meter it's tied to, capped by that meter's own 12-month history.
So a shop on its own LEU meter needs its own system. LEU's documents don't say how it treats a second system on one parcel. Read with the no-aggregation rule, the likely answer is a separate pre-approval, a separate $839 meter, and a size capped by the shop meter's own use. That's a reading of the documents, not a ruling. Ask LEU in writing before you sign.
Outside city limits, on PG&E wires: often yes. PG&E's Solar Billing Plan aggregation lets one system serve several meters held by the same customer of record on the same, adjacent or contiguous parcels. List every meter before installation; PG&E warns that adding or switching meters after interconnection may cost you solar credits. How a well-pump agricultural meter is treated once Ava supplies it is not something we found in writing, so ask PG&E and Ava. Statewide rules let you size to annual load, or up to 50% above it if you attest to the need.
Ava's Solar Billing Plan terms add 2.5¢ per kWh to exports between 3 and 8 p.m. for customers not on CARE or FERA, and Ava trues up credits in April. Ava is enrolling San Joaquin County solar customers between June 2026 and April 2027, so ask when your account moves. Hourly export values change, so this page gives no dollar figure for them.
Worked example: same property, two sides of the city line
Illustrative calculation · not a quote. A household uses 11,000 kWh a year on its house meter and 4,000 kWh a year on a separate shop-and-well meter (illustrative). It wants one south-facing ground array behind the shop to cover both: 15,000 kWh ÷ 1,653 kWh per kW = about 9.07 kW, so a 9.0 kW design (about 14,877 kWh a year). The 1,653 kWh per kW yield is a modeled estimate (PVWatts, ground mount facing south at 30°, Stockton weather about 11 miles from Lodi, no shade). LEU checks size with its own EPBB estimate, which may differ.
Address A, inside Lodi city limits (LEU). One array cannot serve both meters. The options:
- House meter only. Cap: 11,000 kWh ÷ 1,653 = about 6.65 kW, so a 6.6 kW design (about 10,910 kWh a year). The shop meter stays on the grid.
- Two systems. 6.6 kW on the house meter and 2.4 kW on the shop meter (4,000 ÷ 1,653 = 2.42 kW; 2.4 kW makes about 3,967 kWh). Each needs its own LEU pre-approval and solar meter. At the posted single-phase fee of $839, that is $1,678 in meter fees before permits.
- What each kWh is worth. Used at home, it avoids 14.28¢, 15.81¢ or 33.66¢ depending on the tier, plus the monthly ECA (3.17¢–5.13¢ in July–September 2026). Exported, it earns 8.43¢ (July 2026–June 2027).
Address B, Lodi-area acreage outside city limits (PG&E wires, Ava supply). One 9.0 kW array can serve both meters under PG&E Solar Billing Plan aggregation, if both meters are in the same customer's name on the same or adjacent parcels and are listed before interconnection. Its 14,877 kWh is within the 15,000 kWh annual load; up to 22,500 kWh would be allowed with an attestation. County permit; SolarAPP+ does not cover ground mounts.
| Illustrative calculation | Address A: inside LEU | Address B: PG&E wires, Ava supply |
|---|---|---|
| Meters one array covers | One | Both, if listed first |
| Design | 6.6 kW house only, or 6.6 + 2.4 kW as two systems | One 9.0 kW array |
| Utility meter fees | $839 per system ($1,678 for two) | Not captured here |
| Permit desk | City of Lodi Building Division, after LEU pre-approval | San Joaquin County |
Now check the price per watt (the price divided by the system's DC watts). State benchmark: EcoGen Solar Cost Index, September 2026 Edition, prices as of September 25, 2026: $2.85/W for California, a modeled installed cash price for solar only, before incentives (how the index is built). For 9.0 kW: 9.0 × $2.85/W = $25,650.
Illustrative calculation. A ground-mount bid of $33,900 lists three ground lines separately: a 180 ft trench ($3,600), piers and ground racking premium ($2,700) and a shop subpanel ($900), all illustrative. Whole bid: $33,900 ÷ 9,000 W = $3.77/W, which looks 32% above the benchmark. Array only: ($33,900 − $3,600 − $2,700 − $900) ÷ 9,000 W = $26,700 ÷ 9,000 W = $2.97/W, about 4% above. The gap is the ground work, not the panels.
Inside LEU, add the posted City and LEU fees, which a statewide benchmark leaves out: about $1,495 for one system up to 15 kW ($375 solar permit, $1 and $13 state fees, $839 meter, $89 LEU electrical permit, $178 LEU inspection). Two systems add at least a second meter fee; ask the City whether the second array also takes its own permit.
How the proposed service would plan your Lodi property
Proposed service. NorCal Solar Services is a proposed solar service for San Joaquin County homes, built around ground-mount and rural-property solar: wells, shops and acreage, with trenching, setbacks and utility differences in one plan. Coverage of Lodi is proposed and not yet confirmed.
In Lodi the plan would start with the meters. For a city lot with one LEU meter and a usable roof, it would recommend a roof array, not a ground mount. The ground-and-acreage work fits rural parcels outside the city and city lots with a detached shop.
| Lodi situation | What the proposed plan would cover |
|---|---|
| City lot, one LEU meter | Main-house roof array under LEU's cap, EPBB-checked; LEU pre-approval first; fees itemized; ground option only where Building and Planning allow |
| City lot with a detached shop on its own meter | A written meter plan; a second system and LEU meter if the shop is covered; shop-roof structural check; trench route if the array sits away from its meter |
| Vineyard or rural parcel outside city limits | County permit; PG&E aggregation across house, well and shop meters, listed before install; Ava enrollment timing; an 811 ticket; the 10 ft clear perimeter; trench and setbacks on a scaled site plan |
| Existing NEM system from before 2017 | The cost of moving the whole system to Schedule EP, priced before any panels are added |
Ground work would sit on separate price lines (trench per foot, piers, racking, conductor upsizing, subpanel) so you can run the $/W check yourself. The same split is worked through in the homepage's roof-versus-ground cost example.
Batteries and EV chargers would be optional, separately priced lines. LEU reviews a battery with the solar system or as a later permit, and it must disconnect when Lodi's grid voltage is lost.
Which permit desk your layout goes to
In Lodi, the utility approves before the City does. Plan in this order, from LEU's Steps for Going Solar and the Building Division's rooftop solar permit procedure (January 2026):
- 12-month usage history. Get it from LEU for every bidder.
- LEU pre-approval. The contractor submits plans and size in PowerClerk. Allow up to two weeks.
- Building permit. The Building Division reviews within 72 business hours of LEU approval and a complete application. A main-dwelling rooftop system that isn't ballasted (held down by weights) can use SolarAPP+, an online instant-permit check. Main electrical panel changes and EV chargers need separate permits.
- Install and City final inspection. A re-inspection costs $178.
- LEU solar meter, usually within ten business days of the City final.
- Permission to operate (PTO). LEU leaves a door hanger, then issues the PTO certificate.
The City's January 2026 checklist adds items to raise early: a lockable AC disconnect within 10 ft of the meter and in sight of it; 3 ft roof pathways; the main-panel limit (solar breaker at most 20% of the panel rating, or a passing 120% busbar calculation); and a revised roof plan if LEU cuts panels. It's written for systems of 10 kW AC or less; ask how a larger one is reviewed.
Ground mounts and shop roofs inside the city. SolarAPP+ covers only the main dwelling's roof, and the posted procedure is for rooftop systems. Ask the Building Division which review a ground or shop-roof array takes. Ask the Planning Division where a ground array may sit; the Development Code and zoning map set setbacks and height. LEU adds three ground-mount rules: meet National Electrical Safety Code clearances, disclose every easement, and call USA North (811) before trenching.
Parcels outside city limits. San Joaquin County Community Development permits roof and ground arrays. SolarAPP+ doesn't cover ground mounts, so expect plan review, and ask whether Planning signs off first. Call 811 at least two working days before digging. The 2025 California Fire Code (§1205.5.1) calls for a 10 ft clear, brush-free area around a ground array, which matters beside dry grass or vineyard rows; confirm the current requirement with the county.
Have solar from before 2017? Price the switch before adding panels
If your system was connected before LEU closed net metering in September 2017, you may still bill on NEM. LEU lets existing NEM systems keep it for 20 years from interconnection, and a new owner of the house keeps it too. A system connected in 2006 or earlier has already reached that 20-year mark, so check which schedule your current bill shows.
The catch: expanding a NEM system moves the whole system to Schedule EP. You can't keep the old panels on NEM and put the new ones on EP. So "adding a few panels" also moves every old panel's exports to the 8.43¢ credit.
Before an expansion quote, ask for two numbers: your bill with the system as it is, and with the expanded system fully on EP. If the second isn't clearly lower, leave the system alone.
Lodi quote checklist: ask before you sign
Ask every bidder these; the quote checklist on this site carries them.
- Which utility did you assume for each meter? Check it against the bill: LEU inside city limits, PG&E with Ava supply outside.
- Show each meter's 12-month history with the EPBB estimate beside it. Inside LEU, the estimate must not exceed the history, meter by meter.
- Which meter does the array feed? If a shop or well has its own LEU meter, the quote should show a second system or say plainly the meter isn't covered.
- What export credit did you use? Inside LEU: 8.43¢ per kWh for July 2026–June 2027, labeled as this year's number.
- Is this a PPA? LEU doesn't allow PPAs. A lease is allowed as financing.
- Are the City and LEU fees itemized? Look for the $375 permit, $1 and $13 state fees, $839 meter, $89 electrical permit and $178 inspection. The $839 meter fee is LEU's posted figure for July 2026–June 2027; the City's permit sheet says to confirm current LEU fees with LEU.
- Do I already have NEM? If yes, the quote must show what moving the whole system to EP does to the bill.
- What is the solar-only price per watt? Remove trench, piers, racking premium, subpanels and battery, divide by DC watts, and compare with the $2.85/W state benchmark.
- Does the payback assume a 30% federal tax credit? It shouldn't. The IRS Residential Clean Energy Credit isn't available for systems placed in service after December 31, 2025.
- Will the system be finished before January 1, 2027? EcoGen's California guide notes the state's property-tax exclusion for new solar applies only to systems completed before that date.
- Does any line claim a Lodi rebate? LEU says it has none.
- Who files what? LEU pre-approval, building permit, 811 ticket, inspections and PTO, each with a name beside it.
LEU also advises: get at least three written estimates, check each contractor's license with the Contractors State License Board, and read the CPUC's Solar Consumer Protection Guide before you sign.